Command Centre

Riverside Court · Block B

14-storey commercial tower · Riverside Drive, Westlands, Nairobi · contract sum KSh 1.84B

Mjengo AI 82% confidence

Long rains threaten a 6-day slip on the critical path

Heavy rainfall is forecast 1–5 June. The Level 8 slab pour and external works are exposed (idle-plant exposure ≈ KSh 3.2M). Bringing forward blockwork and M&E first-fix while the curing window holds recovers 4 of 6 days.

Progress
58%
+6% this month
Schedule
−6 d
behind baseline
Forecast cost
1.87B
+1.6% vs 1.84B
Open items
18
5 awaiting you

Project lifecycle

58% complete
Planning
Done
Approvals
Done
Procurement
Done
Construction
In progress · 58%
5
Handover
Upcoming

Needs your attention

View all
  • RFI-039
    Substation slab penetration
    Otieno & Associates · Structural Engineer
    Overdue 6d
  • VO-08
    Substation capacity +1000 kVA
    Pending valuation · J. Mwangi & Co. (QS)
    KSh 4.2M
  • IPC-14
    Interim payment certificate
    Due 06 June 2026
    KSh 96.4M
  • NCA
    Quarterly compliance return
    Due 14 June 2026
    15d