Riverside Court · Block B
14-storey commercial tower · Riverside Drive, Westlands, Nairobi · contract sum KSh 1.84B
Mjengo AI
82% confidence
Long rains threaten a 6-day slip on the critical path
Heavy rainfall is forecast 1–5 June. The Level 8 slab pour and external works are exposed (idle-plant exposure ≈ KSh 3.2M). Bringing forward blockwork and M&E first-fix while the curing window holds recovers 4 of 6 days.
Progress
58%
+6% this month
Schedule
−6 d
behind baseline
Forecast cost
1.87B
+1.6% vs 1.84B
Open items
18
5 awaiting you
Project lifecycle
58% completePlanning
Done
Approvals
Done
Procurement
Done
Construction
In progress · 58%
5
Handover
Upcoming
Needs your attention
View all-
RFI-039
Overdue 6dSubstation slab penetrationOtieno & Associates · Structural Engineer
-
VO-08
KSh 4.2MSubstation capacity +1000 kVAPending valuation · J. Mwangi & Co. (QS)
-
IPC-14
KSh 96.4MInterim payment certificateDue 06 June 2026
-
NCA
15dQuarterly compliance returnDue 14 June 2026